Monday 19 May 2014

Achieving continuous product delivery in Set Top Box (STB) software projects: Challenges & Expectations


The story all software product development teams face at some point in their journey, not necessarily unique to digital Set Top Box (STB) software development: So you entered the product development space, setup a small team that delivered the unimaginable - you got your product out in record time. Customers are pouring in, marketing & strategy are imposing an aggressive roadmap. You've set the pace, possibly surviving through possible death-march-like project deliveries, and now you're expected to do more: Scale! You need to scale your product development & operations to support an aggressive business roadmap, the competition is intense, you're charged with figuring out how to deliver releases to market as frequently as possible in one calendar year - so you set the target of a releasing every quarter, or rather, inherited a Product Roadmap that showed Market Launches every quarter…

You barely survived getting one release to market with quite a small team, how do you scale your operations to satisfy the business demands? What behaviours and habits do you change? What changes can you make to your current practices? You must've been using some form of Lean/Agile technique to meet the original aggressive delivery, is the process that was used before enough, can it scale to get you from where you are now, to where you want to be? What are the implications of achieving continuous product release flow, in an environment, that is typically unique to Set Top Box hardware & software development?

In this post I highlight just one possible framework that cuts through all the areas involved in product engineering of Set Top Box software releases. I will not go into detail behind the intricacies of this environment (search my blog to learn about that) - instead I will map out by using a few pictures that shows the scenarios around achieving continuous product releases to market.

The pay TV space is becoming highly competitive, especially with the likes of online / OTT (over-the-top) players like Hulu, Netflix, Amazon, etc - such that traditional operators are hard pressed to up their game from providing the clunky, almost archaic standard TV experience to a more slicker user experience, offering advanced features, integrated with traditional linear services with additional services aimed at stifling the modern competition. No longer can these traditional pay TV providers release new software once a year at least, users having become used to frequent updates with new features on their smart devices every few months, people are becoming more and more impatient with bugs that go unfixed for some time…Nowadays, it is expected that set top boxes are updated with new features as often as possible. 

With this in mind, how does one structure a product engineering department to cope with this demand? How should projects be managed? What do we expect from teams? What are the implications of reaching continuous delivery? Where does a typical agile/scrum team fit in? Is Scrum even a preferred method, or do we choose a hybrid model?

[This is still very much a work in progress, made public to get feedback/advice from other practitioners out there...]

Thursday 2 January 2014

Architecture Interview Questions


I've written about architecture topics in the past, especially relating to the role of "Architect" in Digital TV Systems & Software projects. Though I'm no architect myself, although I could very well have become an architect if I chose to maintain on the purely technical path; I still have to be across the technical disciplines at the high level, when it comes to program or project managing large-scale technical projects. 

When I start or join a new project, one of the first things (apart from familiarizing myself with the product spec) I do is to seek out the architects, looking for any technical information in the form of design,
(document/wiki/etc) that scopes the high level system design or architecture that we're trying to implement & deliver. 

Failing that, having found no clearly defined architect role, I would go about setting up this role as a matter of urgency. No architect means no technical ownership, means flaky interfaces, chaotic system integration points, and a very bumpy project ride lays ahead!

In the past I have worked very closely with many great architects, both as an engineer as well as manager, that I've learnt from this experience enough to know what to look for when seeking out architects. If a project requires it, I do get involved with the interviewing architects, system integration managers, project managers and other roles. 

I thought I'd share a list of some of the questions I generally tend to ask when interviewing for the role of Architect in a Software/Systems project - hope you find it useful. If you read my other posts on architecture, you will get to understand I have a more holistic expectations from architects, rather than just answering this list of ~100 questions!

Wednesday 23 October 2013

Career Ladders: Avoiding chaos and anarchy in Software / Systems Projects


This post is part rant & part structured discussion around the topic of career development in the domain of Software & Systems Engineering. I have been in the business of core software engineering for fifteen years (15), and was fortunate to experience working with highly rated professional companies (from Silicon Valley, internationally renowned) whose sole purpose was producing software systems from scratch, including as providing software design services to other software companies - these companies maintained true to engineering as a discipline.

A graduate engineer would enter the company with a fairly good idea of the where he/she is starting, and the various options & opportunities that lay ahead in terms of career growth, and, depending on the company - this graduate could spend

the next 10-15 years with just one company alone and never get bored, traversing many job disciplines as he/she so desired. 

This is the baggage (rightly or wrongly) that I come with, and hence my surprise to learn that some companies in South Africa are still making a serious mistake of not having a simple template that maps roughly the career ladders for the team, covering Development/Test/Integration Engineers, Architects and Managers. I firmly believe this is a recipe for chaos & anarchy that must be avoided as far as possible, and the solution to this problem is to map out a simple Career Jobs Ladder for your technical department.

Don't get me wrong: I am all for meritocracy, flexibility and not bureaucracy - but it really irks me to see things happen in the workplace that just don't make sense, especially when promotions happen when there is no real truth, track record or backed-up peer recognition that warrants a role / title change. 

I have seen the following happen as an example of chaos:
  • An integration engineer with no prior design or architecture experience is promoted to Architect
  • An software engineer with no prior architecture accolades is promoted to Architect
  • A software engineer with no prior team leading, people management or facilitation experience is promoted to Scrum Master
  • A team lead with no prior project management or scrum mastering track record becomes an Agile Manager
  • An integration engineer with no product management experience becomes a Product Manager
  • A new recruit with no prior experience in the technology domain joins as a Senior Solutions Specialist
  • A new architect who has never architected any product before enters as a Solutions Architect
  • An enterprise architect who has never delivered to market any real enterprise-class systems product that has a user base of more than fifty is made Enterprise Delivery Architect
  • A component architect who's only worked on a single software module / component becomes Enterprise-wide Solutions Architect
  • An integration engineer who's only experience in embedded devices joins an enterprise systems integration team as a Senior Integration Specialist
  • An automation specialist or tech lead who is misunderstood as the Head of Automation
To an observer, the above scenarios are candidates for chaos (What do all these roles mean? What's the job spec? Is there a clear map that shows the progression of one role to another?, etc. etc.), although these cited migrations would not be that far fetched if there was a career ladder to hand, that facilitates the growth path - that can be used to take the individual on the journey to reaching his/her desired goal....

And this is where anarchy comes in (again, a little rant on my part):

Tuesday 30 July 2013

Agile Architecture - Roadworks Analogy

I've had some interesting, somewhat frustrating conversations recently, around the roles, responsibilities and expectations of a Systems Architect. Refer to a previous post on how I broke down the various architecture roles for Digital TV Systems Projects.

What triggered the recent discussions is around understanding how architecture fits in with the Agile process. Before people who think themselves Agile Aficionados (Agileficionados) singing praise that architecture can be done just-in-time, please remember the context which I refer to: Embedded Set-Top-Box or Backend Systems Engineering.

We are not in the business of writing web applications, smart phone apps, tablets, or any desktop application, or even a web site -- where these environments are usually proven, solid and stable that fosters rapid application development cycles.

Digital TV projects, especially Set-Top-Box projects are a little more complicated than iterating through web page developments, switching versions easily through redirecting URLs, eliciting real world customer feedback for alpha/beta sites or apps, etc. STB projects generally involved multiple vendors or software suppliers, each with its own development processes. Testing is often done in a limited lab environment, whilst real world customer feedback demands an end-to-end engineering system to be deployed in a live broadcasting environment (which is currently in active use, generating revenues for the PayTV operator, so engineers better be damn sure they're not going to disrupt business operations, etc).

So some STB project teams are indeed embracing Agile (or at least trying to be Agile in the context of their component-worlds). I have written about the difficulty of doing Agile in these projects that I'm not going to repeat here. How then does one deal with the concept of architecture in Agile? Do we stick to Just-in-time, just enough or do we embrace a little structure and discipline, in keeping with Mile-wide, Inch-thick view of the future, but not waste time with too futuristic features??

For Digital TV projects, I prefer the mile-wide, inch thick approach, where we're looking at least a year ahead into the future, to develop new features and enhancing the roadmap. This is especially true for long lead features, like Recommendations, Targeted Advertising, Home Networking, or even designing the next evolution of your Middleware or EPG. And I believe that Architecture, can still be done incrementally, in an Agile-manner, although with a little discipline called foresight and pragmatic proactivity. To support this picture, I created the Paving-the-Road analogy:

Tuesday 26 February 2013

Modeling Software Defect Predictions


In this post I will share yet another tool from my PM Toolbox: A simple method any Software Project Manager can use for predicting the likelihood of project completion, based on a model for defect prediction. This tool only scratches the surface of real software engineering defect management, but has nevertheless proved useful in my experience of managing a large software stack. For instance, this tool was borne from my direct experiences as a Development Owner for a large Software Stack for STB Middleware that comprised of more than eighty (80) software components, where each component was independently owned and subject to specific defect & software code quality requirements. I needed a tool to help me predict when the software was likely to be ready for launch based on the health of the open defects; as well as use it as evidence to motivate to senior management to implement recovery scenarios. It was quite useful (and relatively accurate within acceptable tolerances) as it offered perspective of a reality that more often than not, people underestimate the work required to get defects under control, the need for predicting project completion dates based of defect resolution rates, depending on the maturity of the team is often also misunderstood. 

I created the first instance of this tool back in 2008/2009, the first public version was shared in this post on Effective Defect & Quality Management. Since then, I've upgraded the tool to be more generic, and also significantly cut down on the number of software components. I still use the tool in my ongoing projects, and have recently convinced senior management in my current project to pay heed to defect predictions. 

Friday 7 December 2012

Types of Digital TV Projects, Decision Factors & Typical Duration

In this post I will discuss the various types of Digital TV projects that I've come across over the last twelve (12) years. Although the DTV system is a complex one, and in theory, there are many different permutations and combinations of possible projects, we should not forget that on the part of the Pay TV Operator, it is quite an expensive affair, and therefore these guys are quite resistant to change. Initial costs in setting up the broadcast network must be made up in as short a time as possible (ROI in less than 5 years maybe), subscriber growth must be on the increasing trend, competitive threats kept at bay.

Depending on the market dynamics, some PayTV operators (especially Europe & North America) have strong competition, the market is quite open and those regions usually have a strong regulatory body that promotes a free market, competitiveness and most important of all, the right of consumers to choose. Whilst in other markets such as Africa and Middle East, the PayTV operators that were first to get in when the time was right, are usually market leaders, the dominant player and lack any strong competition.

Regulatory bodies in this region are either non-existent or immature in its abilities in governance and promoting a free market based on consumer choice (South Africa is a good example: not generally consumer driven, although recently this has seen a change with the introduction of the Consumer Protection Act but is still far from having an SA-equivalent of the UK's Ofcom for example ICASA doesn't come close). In the Asia/Pacific markets, there is a growing number of PayTV operators, where competition is rife, time-to-market more important over say, user experience or innovative features (I've seen this with my own eyes, for example - in India, there are some operators that have got products that look like they're built on eighties technology)...

I've set myself quite an ambitious task (as usual). The nature of DTV projects vary, depending on which side of the fence you're sitting on. Of course, all projects that generate revenue are driven by the PayTV operators themselves. If you're a software vendor, say Middleware or EPG Application, you will have a mix of customer delivery projects and internal R&D projects. Both projects have their own challenges, involve various factors that influence decision-making; and both can largely be estimated using general guidelines (that are usually based on performance of past projects).

In this post, I'll discuss projects from the PayTV Operator's point-of-view, in terms of typical use cases. In a future post I will touch on typical R&D projects and what drives primarily software vendors operating in the DTV product space.

Breakdown:

Friday 16 November 2012

Process for Fast-Tracking Issues - The Daily Scrub


In this post I'd like to share a simple, yet effective process to managing the defect discovery phase, typical experienced during the early stabilisation phase of launching a STB product. The process does not only apply to STB projects, it can be used for Headend projects; or even general Software Projects that involve a number of components requiring system integration. Since the bulk of my experience comes from STB projects, the information presented here thus has a bias towards STB projects.

The material presented here is not that ground breaking, really. If you've been in the business of delivery DTV projects for a long time, then you probably have a tried and tested way of managing the system integration processes. However, if this is the first time you're involved in system integration, you are either a PayTV Operator taking more ownership of SI (System Integration), or you might be a professional services outfit and have won your first big project - If you fall into either of these categories, then I have no doubt that you'll find this useful, at best, trigger to review your currently planned strategy.

As an aspiring independent consultant, the Scrub Process is yet another addition to my PM Toolbox. Recently I had to present this process to a project team, who's processes were a bit old-fashioned and rather rigid, and slow. I needed a medium to express the concepts of gaining more efficiencies out of the SI Process, thus put together this presentation to communicate the idea, which I'll only briefly touch on here. For more details, please download the presentation.

Thursday 15 November 2012

Set-Top-Box (STB) BootLoader Management Template


The Set-Top-Box Bootloader is a crucial piece of software (actually firmware that is generally burnt into (ROM) Read Only Memory, usually One Time Programmable (OTP)) that performs not only the vital job of the classic bootstrap (Power on, boot, launch application) for the device but also is fundamental to applying software updates to the system.  Like in PCs, the bootstrap is the initial code that is loaded that generally performs a self-test to check if the device configuration is OK, and looks for an image to load that essentially boots the device into operation, ultimately loading the EPG application.

The Bootloader is generally implemented as very low-level code, with limited set of drivers to enact the basic hardware functionality, with the focus of occupying as small a footprint as possible. There are different types of Bootloaders implemented in STBs, generally known as "n-stage" Loaders. Typically you find a Singe-Stage Bootloader and Two-Stage Bootloaders. A Single-Stage Bootloader entails an all-encompassing loader, self-sufficient, not requiring the help of another bootstrap to continue the boot process. Whereas, a 2-Stage Bootloader, as the name suggests, includes a secondary stage, that kicks of a higher-level bootstrap to facilitate the loading of subsequent system components.

As a STB Project manager, there will be a occasions where the Bootloader requires special attention. This is especially true for projects involving brand-new hardware, different Middleware or Drivers. Generally though, the Bootloader is closely coupled with the Target Hardware: Change in Hardware implies Bootloader changes.  However, if implemented correctly, the software architecture for a Bootloader can be effectively designed like any other software stack, with generic components as a Middleware would, leaving a HAL/Hardware Abstraction Layer open to port for different Hardware devices, thus making the job of supporting Bootloader code more efficient. In some cases, Bootloader is a product in its own right, and many companies and consultants have made a business out of it.

STB Bootloaders could be provided by the CA Vendor, Middleware Vendor, or traditionally the STB Manufacturer, because of the code being so low-level and tightly linked to the physical hardware. In the early days when the traditional medium of delivering software to the STB was through the physical tuner cable, the role of the Bootloader was relatively simple. It gets complicated when we move to hybrid STBs, especially with an IP connection, as this opens up another channel for distributing software updates. IP Bootloaders in STBs is relatively new, and hasn't reached a state of maturity as say, the traditional Satellite STB Bootloader. Bootloader testing is extremely technical and complicated, the security, reliability and resiliency testing is really thorough. For example, when testing a Satellite STB, the Bootloader must deal with all kinds of Signal Quality conditions: Removing the signal feed in the middle of the download process, recovering signal, time-outs and general reliability: pulling out the power during the final stages of the write process, etc.

In an IP Bootloader, the same scenarios are considered, but at the TCP/IP networking level. First and foremost, the STB IP Loader must implement a robust IP networking stack. We had a problem in one of our projects where the Bootloader had hard-coded MAC addresses to Zero! We only picked this up late in the project as we entered the final testing. Such basic scenarios should not get past the first stage. Once we fixed that problem, we then hit stability problems: network jitter, packet loss & general robustness w.r.t. IP-connectivity. The Bootloader software component must be ready and verified well in advance of formal production of the hardware. Remember this component is burnt into the STBs at the time of manufacture. It has to be defect-free, any rework post production is going to be next to near impossible, or severely time constraining, manual reworking that will cost the PayTV operator tons of money. You screw up the Bootloader, you fired!

The above experience thus triggered me to instigate a more formal, rigorous process in managing the Bootloader Workstream, which is presented below.

Template for STB Programme Manager: Bootloader Workstream
If your STB project involves a hardware element then it's most likely to impact the Bootloader. It is essential to highlight this dependency in your project plan, even though you might not be directly responsible for the development & delivery of the said platform. If the project was initiated well, or your organisation is quite mature and have been delivering STB projects for many years, then this workstream happens almost like clockwork, automatically in the background, most likely by your company's STB Hardware / Drivers Porting team.

Nonetheless, defining the key roles and assigning owners to the management of the Bootloader delivery will help clarify and add structure to the overall programme:
  • Product Owner - If you're a broadcaster or PayTV Operator, you need a good understanding of the feature-set and requirements of this component that meets the needs of your business objectives & operations. If you're a component supplier, you still need someone to own the product specification for this component.
  • Technical Owner - Is someone with technical responsibility, generally an architect, who will translate the Product Owner's requirements into detailed technical requirements specification, that Bootloader vendors must implement.
  • Component Owner - The party responsible for implementing, testing & delivery of the Bootloader component.
  • System Integrator: Low-Level & System High Level. The responsiblity of the assigned STB System Integrator to prove the integration of the said software component.
  • Quality Assurance: Security & Customer. Generally CA Vendors provide certificate of approval of the Bootloader, as it has to pass strict security criteria, remember the CA is responsible for generating millions in revenue (this is generally known has Low-Level code testing). The Bootloader therefore has to be secure to prevent intrusion, compromising the integrity of the STB, leading to piracy. The PayTV operator also performs ATP as the Bootloader must adhere to various business scenarios for software download, upgrade, resiliency & recovery modes. Operator testing is generally referred to as High-Level Code or Customer Code testing.
  • Project Team. There must be a Project Manager assigned to manage this Workstream. There are generally many dependencies at the System Integration level, so this is best assigned to an SI Project Manager.

Simple Template for Bootloader Workstream


Monday 1 October 2012

Milestones Template for Managing & Tracking a Digital TV Programme


Do you keep a PM Toolbox close to hand?
One of my most common questions I ask candidates interviewing for Project Management or Programme Management positions is the subject of maintaining your own personal set of tried-and-tested tools you've come to depend on in your career with managing projects: Do you have any tools or templates that you keep with you as a standard reference such that you hit the ground running on your new project? If so, what kind of tools do you most value and cherish, and why??

Surprisingly though, most of the people I've interviewed either settled for the generic tools that are sold by the various PM Methodologies (Prince2, PMI, PMBOK, Scrum) - I've come across very few people who keep an arsenal of personal tools ready-to-hand to pick-up and use on their next project.  I too am guilty as charged, very often relying on memory and previous project documents to pick-up and use as a starting point.  I have however, started to collect my own set of tools that I'm willing to share with everyone, in the interest of knowledge-sharing and collaboration, the first starting with this post on a Template for Tracking Milestones on a Digital TV Programme.

When I used to be a developer back in the day, I had my own set of code samples that were generic enough to be re-used, my recommended debugging tools, libraries, parsers, open source projects, and so on. Along with your trusted book on Algorithm Design, Software Architecture Patterns and System Utilities - necessary tools for the job, like any other trade.  So too, for people involved in various aspects of Project Management, you could keep your very own toolbox that can help speed-up the much repeated, but often required aspects of the job.

A Preview of my PM Tools Backlog
Because my background really is around Digital TV Systems Projects, an area that has still a lot of life to survive the next 10-15 years, especially since Digital TV (DTV) is really only just beginning to fire up in emerging markets of Africa, India & China, there will still be a need and demand for such Project Managers.  I aim to share as much knowledge as I've gained through practical experience, by making available the tools I've come to trust and use in both past and current projects alike:
  • Generic Model for Tracking Milestones in a DTV Programme (this post)
  • Programme Model for Staged Deliveries for a DTV Launch
  • A Modeling tool to Estimate & Predict Realistic Time to Market (Climb to Launch)
  • Set-Top-Box Software Integration Release Schedule Process
  • A Generic Risk Register for a Typical DTV Programme
  • A Template for a typical DTV Project Charter or Software Development Plan
  • A Template for Managing a DTV Project based on an Agile Product Backlog
  • RAG Template Options
  • Models for Programme Organizational Structure
  • Methods for Controlling Quality: Effective Defect Management
  • Methods for Managing STB Software Development Processes
  • Template for Defining Bootloader Development Work-Stream
  • DTV Projects Matrix - A guide to understanding the permutations & combinations of system impacted components in a variety of different projects, arranged by complexity and rough estimations of project life-cycles
So I intend to release a tool as often as I can, in the hope that other Project Managers can use, learn, benefit and adapt these tools in their own day-to-day projects...

PM Toolbox #1: Generic Milestones Template for DTV Programme Management
This tool is all about summarizing and tracking the various Milestones that must be met in order to achieve a successful DTV Project Delivery. It is essentially the fifty thousand foot view of the high level work packages (or Work Breakdown / Sub-Projects) that essentially make up the various streams of delivery in the overall Programme.

The tool serves the purposes of communicating clearly the status of the overall Programme, which is what Senior Stakeholders are interested in.  It also serves as the master Project Plan for the entire programme, around which dependent sub-projects or work streams must deliver to.  Whilst it might come across as a simple table, list with columns, it is nevertheless a powerful tool in managing and tracking the overall project.

Download the Tool!
Please click here to download the tool. It is simply a Microsoft Excel spreadsheet that provides a list of milestones, for each milestone, we track the following criteria:

  • Milestone Name / Title - The actual event that manifests as an identifiable achievement of a goal
  • Company Responsible - The company or vendor who is assigned responsibility and accountability for delivering the result
  • Actual Plan - Tracks the current forecasted planned delivery date
  • Original Plan - Tracks the baselined original dates at the inception of the project
  • Acceptance Criteria - For each milestone, the agreed acceptance criteria (at high level)
  • Dependencies - For each milestone, detail the associated dependencies the milestone has, preventing successful completion
  • RAG Status - An agreed RAG convention to be used to summarize the status of the milestone
  • Recovery / Mitigation Actions - A set of actions to be taken to implement recovery scenarios
  • RAG Comments - A note on the current state of affairs
  • Project Work-Stream Owner - The name of the Project Manager or Owner assigned responsibility and accountability for delivering on that milestone

The table is pre-populated for you with the standard set of milestones I usually expect from a typical DTV Project. I have also pre-filled in scenarios for Acceptance Criteria, Dependencies as well as listed your typical Recovery Scenarios.  The tool comes with an information page that instructs you how to go about replacing the template with actual project data.

What is a Digital TV Programme: Players, Concepts, Milestones?
In order to appreciate the nature of a Digital TV Systems Project, you have to first indulge in a brief overview of what a Digital TV System entails, the players involved and the typical project configurations expected:

So now that you've read this background material, we can start exploring the make-up of the Milestones Tracking for a typical DTV Project:

The template assumes a DTV Project that impacts the entire end-to-end system of a PayTV Operator's value chain. Not all DTV projects encompass such massive changes across the board, there are some projects that involve just Set-Top-Box (STB) Software-Only changes, other projects might only involve introducing a new STB hardware device (decoder) with no changes to software. There are also Headend projects dealing with routine maintenance and enhancements as well.  I plan to create and share a matrix of your typical DTV project-based scenarios one day...

The tool assumes a big-bang project that involves the following players:

  • [PAYTV OPERATOR] - This is generally the PayTV Operator that is implementing the project to deliver or enhance their existing systems (e.g. BSkyB, DirecTV, Multichoice, etc.).
  • [STB MANUFACTURER] - The designated company responsible for the hardware design and manufacture of the client Set-Top-Box (STB) (a.k.a. Decoder), supplying related device Software (Drivers).
  • [MIDDLEWARE PROVIDER] - The company or service provider responsible for developing the software operating system for the STB, including providing value added services that enables rich Application Development for STB User Experience (i.e. the Electronic Programme Guide / EPG).
  • [EPG UI DEVELOPER] - The company or service provider a [PAYTV OPERATOR] usually employs to develop the STB client application or user experience. There is a growing trend with PayTV Operators electing to do this development in-house.
  • [INTERACTIVE APPLICATIONS DEVELOPER] - The company or service provider a [PAYTB OPERATOR] employs to implement value-add interactive applications that are built on the [MIDDLEWARE PROVIDER]'s platforms. Increasingly PayTV operators are also electing to do in-house development, or to contract this work out to the same [EPG UI DEVELOPER] or indeed have a third-party application development house contracted.
  • [HEADEND PROVIDER] - The company or service provider responsible for developing the backend or headend systems. Typically this is the same as [MIDDLEWARE PROVIDER] since the technologies are inter-related, but there are some PayTV operators that prefer open standards and choose to use a variety of suppliers to manage their risks (i.e. not to have all their eggs in one basket).
  • [SYSTEMS INTEGRATOR] - The company or service provider with sole responsibility and ownership for proving components & systems are well integrated and deliver on the desired functionality and expectations of the programme.  There are many levels of System Integration, depending on the [PAYTV OPERATOR]'s budget, etc. Typically though, it seems that [PAYTV OPERATOR]'s are aiming to be more independent from their service providers in taking the plunge of owning not only the System Architecture but also the System Integration delivery aspects of the programme.
With these players in mind, the Programme can then be translated to obey the following high-level concepts  in translating detailed deliverables or milestones (The detailed breakdown of the plan is a topic for another post):
  • STB Manufacturer Hardware Delivery
    • Hardware Design Specification
    • Remote Control Design Specification
    • Packaging & Artwork Specification
    • Hardware Acceptance Testing
  • STB Software Delivery
    • Device Firmware Bootloader Software Ready
    • Device Hardware Platform Driver Software Ready
    • Middleware Component Functionally Complete
    • UI / EPG Component Functionally Complete
    • Interactive Applications Functionally Complete
  • Backend / Headend Delivery Functionally Complete
    • Broadcast Components Operational
  • Systems Integration
    • STB Integration Functionally Complete
    • Headend Components Integrated
  • Launch / Deploy Product
    • All Acceptance Criteria Met
    • System has acceptable level of defects
    • Business decision granted for Launch
This is just a summary of the deliverables one can track. The tool provides a sample of 34 Milestones that drill down into the finer details.

In the next post I will spend some time explaining what some of these milestones mean, and how one should realistically go about planning the various work-streams, such that dependencies are minimized whilst simultaneously running multiple sub-projects in parallel.


Summary
This is a first draft, a brief attempt at sharing what I think is a powerful tool to aid Project Managers in managing Digital TV Projects.  I have for now, assumed the reader is familiar with the territory and therefore have excluded explanations of describing what the different sub-projects entail, etc. My aim was to share this tool with already practicing Project Managers in the DTV trade, to solicit feedback and share new ways of working, etc.
Some people might think I'm giving away some of my crown jewels by sharing this knowledge, that I'm forsaking my competitive advantage, etc...but I don't think so. I've laid out a simple framework that can be useful to others. There are many templates and tools out there to aid Project Managers, the success of a project delivery lies not in the templates, but in the project manager's knowledge, wisdom and tenacity of execution and implementation....


Thursday 28 June 2012

Managing Large-Scale Projects using Agile, Part 3 - Product Management Methodology


Agile Product & Project Management Model - Large-Scale Set-Top-Box Development Project
A while ago I started writing about my experiences with managing large scale software development projects using the Agile philosophy of very Disciplined Agile Delivery (DAD). In order to do this, I had to first introduce some context & background in the three previous posts leading up to this one, the last post dealing with overall organizational challenges. Now the scene is all set to discuss the actual Agile model we eventually implemented, that continues to stand the test of time: 4 years and is still running quite strong to this day.


Some Background Material
Quick introduction to the world of digital TV
What is a Set-Top-Box?
What is an EPG?
What in the world is Sky TV?


Disclaimer
The experiences I'm writing about is about past projects that I personally worked on or touched in my time a Middleware Development Owner & Middleware Products Manager, that are very much in the public domain:
BSkyB replacing OpenTV HDPVR with NDS technology
Fusion is the new NDS Mediahighway to displace OpenTV
BSkyB Launches new HDPVR
Sky Italia replacing OpenTV HDPVR with NDS Mediahighway
Sky Deutchland delivers enhanced VOD powered by NDS Mediahighway
UPC being powered by NDS MediaHighway


The Project
Take a look at this video clip:





Yes, this is the background project I was fortunate to work on, which forms the basis for my writing on a large-scale software development project. We were responsible for delivering the core software component (Middleware / Operating System) that enabled the EPG (UI Application) to be developed to offer the Sky Anytime+ User Experience.


On the surface, when interacting with an EPG, the user experience might suggest this was a simple application, compared to powerful PC software products like Excel/Word or Adobe Photoshop; surely it can't be a complicated endeavour to create this system? That's not entirely true: Beneath the seemingly simple UI is a complicated piece of software and electronics, so much so, that typical projects such as this one takes at least three years to complete (if all goes well)...


The project was greenfields development on all fronts for the software vendors employed, especially on our side for the Middleware component. But for the broadcaster it was a massively complicated migration project, because essentially we were replacing the full software stack of a legacy deployed based of 4 million+ STBs, with the option for rollback!! 

The project, though massive in size, relied on a core product & architecture team to manage the roadmap and project planning; supported by a very large technical team (software engineers, integrators & testers) that were geographically distributed throughout the world.  Having joined the project a year-and-half into its development cycle, then spent the next two years executing and driving through the implementation and delivery to Launch Candidate builds, I played primarily the role as Middleware Development Owner. I inherited the Agile founding principles of the Programme, which after two full years of practical exposure, resulted in a deep appreciation for Agile, such that all my subsequent projects going forward re-used and evolved the model based on those principles. I later joined the Product Management team that championed the processes through roadshows, training and ramping up new project managers on the "Project Toolbox" required to deliver all future customer projects...

This post is split into the following sections to make for easy reading:

Monday 4 June 2012

Managing Large-Scale Projects using Agile, Part 2 - Organisational Challenges


Organisational Challenges of Large-Scale SDPs
In this post I will describe the organisational challenges with supporting large-scale software projects, especially when the management philosophy is one that promotes agility, or has its roots in adopting Agile/Scrum early with a small team and then ramps up to using a globally distributed project team. Specifically describing the approach we took in managing the example project as described in the previous post. As with any organisation adopting Agile, there must be management support. In some cases organisations have transformed through bottom-up approach, but in an LSSDP project, some initial strategic planning is expected, it's imperative that management support is won at the outset (more about this later...).

Whether you're running a classic, relatively small project (say a team of 15) locally or multiple teams (250+ people), the essential elements of team/project management remain the same, the only difference is the scaling factor as the team expands. In my opinion, the following factors are integral to any software development initiative:
  • Communications: Classic example is the communication model that Brooks provides, with n being the size of your team, the different communication paths is formulated as: n*(n-1)/2  - so a team of 10 would have 45 communication paths, so a team of at least 200 would create 19 900 paths!  With this in mind, pains must be taken to ensure that organisationally, a suitable structure must be put in place to sustain manageable communications.
  • Organisational Team Structures: Flowing from the above problem of communications, each team needs to have an identity - roles, responsibilities needs to be understood. This is a trait common to both small and large teams alike. Defining the structure for the project/organisation through the classic org chart, does help in clarifying the structure.  Even though Agile promotes a flat team, collaborative decision making and participation, it is still useful to ensure the roles are identified and understood.  With a large-scale project though, collaborative discussions and decision making can still sometimes happen, but is extremely challenging. Large scale projects call for a really strong management structure (which involves technical people as well) to ensure momentum in decision making. 
  • Worskpace Environments:  Common challenges to both large and small teams alike, one has to ensure the team's physical environment at which they work, is not only comfortable from a personal space perspective, but also to ensure the workspace can support the needs. For example, Set-Top-Box development/testing requires a desk-space large enough to cater for a few screens (monitors / TVs), ample power supplies, space for mobile stream players, etc.  Agile/Scrum promotes the use of whiteboards for tracking work for example: So do you have mobile whiteboards, fixed boards or what? How do you solve this problem when your team is distributed?? How do you ensure that all your people in all geographic locations have a similar setup as the rest of the world?
  • People Skills / Training needs: Whether you have a small or large team, you will experience the same people challenges: Does the team have the knowledge/skill-set to do the job or task at hand, effectively, efficiently?? How do you build competencies across your team base?  What are the basic fundamental prerequisites of skills/knowledge you need to have? How do you promote transfer of knowledge & training?
  • Peopleware Issues & Cross-Cultural Challenges: Building software is more about people dynamics than implementing technology. If you don't have a well-formed team (Agile/Scrum promotes self-organsing, well-formed teams), which is true for both large and small teams alike, you will experience problems that inhibit the smooth flow of development, impacting your project's delivery.  In a small team, the Team Leader, Scrum Master or Development Manager has more control over this, and has the time to see his/her team through the various stages of Forming, Storming, Norming & Performing. With small teams this process takes time.  With a large contingent of 200+ people, this process is exacerbated, being very difficult to manage and assess due to the spatial and temporal differences in managing distributed teams.  In our project we had people from UK (two locations), India, Israel (Russian, Polish, American, S. African), France & Korea, with third parties from Poland, UK, Ireland & India.   How can you achieve a well jelled team of international players? How do you solve the cultural issues? How do you avoid the frequent Lost In Translation moments?
  • Maintaining Integrity of Software Architecture: All teams need a custodian of the software architecture, typically this is your architect, in our context, the STB architect. Where the team is small, you can have just one STB architect. On a team as large as 200+ people, all implementing a complex architecture, how do you ensure the technical integrity of the architecture is maintained?
  • Tools/Infrastructure/Configuration Management: Like any other trade, a software team need the right tools for the job. Managing your local team it's easy to notice gaps and provide tools; it's far more complicated with distributed teams, since the challenge is in maintaining consistent adoption of tools, i.e. tools should proliferate and be different from team to team (Defect tracking tools spring to mind) so establishing a common infrastructure plan does help in creating consistency for the programme, and maintaining a sense of harmony within the distributed team itself.
In the remaining sections I'll touch on how we addressed each of the above areas referring to the example case study mentioned in my starting post. This post is arranged as follows:

Wednesday 28 March 2012

Effective Defect/Quality Management...


Continuing with the theme of highlighting the core tenets of managing a Digital TV Programme, having previously discussed the following ingredients of a typical delivery:
In this post, I'll share my experiences with yet another stream of activity that in my opinion, is of critical importance to guaranteeing a successful project delivery: Effective Defect/Quality Management. Whilst this topic, when viewed from the concepts of best practices of Software Quality Assurance/Management as described by SWEBOK (Chapter 11 Software Quality Management) -- is an area that could be managed by a Quality Assurance Group, more often than not, it is up to the Programme Delivery Team to monitor, control, track and manage the quality of components deliveries from a variety of component vendors into your programme, more often than not, it comes with the role of a QA Programme Manager if you can afford one, otherwise this is collectively owned by the Project Team.

Depending on the nature, size & complexity of the product/programme, programme manager, apart from managing the programme's planning and delivery schedule, also has to factor in defect management, thinking about the following: 

  • Do you have someone own the Defect Management activity as a sole activity?
  • Is this activity shared between all the project managers on the programme?
  • Do you treat defect management as mostly a co-ordination and monitoring/reporting activity?
  • When is the right time to introduce Defect Managing and Tracking?
  • How hard do we push for Quality Metrics throughout the life-cycle of the programme?
  • What systems are in place to make defect management less of an administration overhead?
  • How do you ensure that all vendors (internal & external) speak the same language w.r.t. defects?
  • Do your vendor's factor in defect fixing in their planning and how do they go about doing that?
  • How much time should your programme schedule allow for defect fixing and stabilisation?
  • How can you manage the expectations upwards to the executive sponsors using predictive analysis and statistical probabilities to target a more realistic launch date based on defect metrics?
  • How do you convince your vendors that instrumenting defect management metrics & reporting is useful as a delivery/schedule tracking mechanism?
  • How do you as a programme manager influence the development/release processes of your development / SI vendors to more effectively deal with quality issues?
  • How do you as the programme manager influence the product owners in accepting your quality delivery criteria?
  • How can you re-use metrics from past projects as inputs to your delivery schedule?
I will not attempt to answer all of the above questions, but instead will focus on an overall strategy that seems to work in the real world, at least from my experience: there is the theory that you can find in all Software Books on Quality Management and all the institutes and bodies of knowledge (SEI, SWEBOK, CMM, ISO9xxx, WikiPedia) -- and then there is the reality of doing what it takes to get a Digital TV project delivered:  Essentially this boils down to doing what is sufficient, what is good enough, what is fit-for-purpose as defined by your business objectives. In this post I will highlight real world practices that exercise the quality principles as outlined in the theory that are sufficiently practical to implement and deliver a quality DTV product.

Regardless of whether your business is a software vendor delivering components to an Operator, or an Operator managing deliveries from several component vendors, the topics discussed in this post are relevant to both Operators and Vendors alike.  As a software component vendor it is in your best interest to prove to your customer, the Operator, that your products are built from sound engineering principles, your quality assurance is second-to-none, and you can guarantee a level of component quality that more than meets the expectations of your customer, the PayTV Operator.

As an Operator, you are so busy managing your operations, that your business is much larger than just managing new technical projects, that you're forced to impose quality criteria on your projects.  If this is not something you're already used to doing, then IMHO, you're overlooking a crucial element of your project's success.  Where relationships between vendors are good, and proven from past experience and deployments of past products, then your can rely on the element of trust.  But in cases where you're taking a risk in adopting new technologies, then it is your responsibility to ensure that Quality Criteria are well defined and acceptable - and ultimately accepted by your vendors.  If you haven't done this already, then you need to re-consider, especially when the expectations are high.

This is a massive post, broken up into the following topics:

Battle-scars (Real-world Project Experience)
Taking a chapter out from a past project experience around the time 2007-2010: An Operator embarked on a programme to replace its existing subscriber-base of deployed HDPVR software with new technology from a different Middleware vendor (company I worked for, I was Development Owner for the Middleware). This new technology that was not yet proven in the market and boasted advanced concepts and radically short time-to-market promises.  Over 2 million people would be affected by this migration, so there was no room for error. Think of the project as replacing all four wheels of your car as well as overhauling the engine whilst the car is still in motion: a seamless transition from one operating system to another, a new user interface with all user's recordings & preferences restored.  To the user, the migration would be unnoticeable apart from an upgraded UI. There was an additional requirement that roll-back to the previous Middleware must also work in the event of disaster recovery.  (Suffice to say, the project was a success and no roll-back was required).

The stakes were high on both the operator-side and vendor-side, as it posed a significant business risk to the Operator; and a massive reputation-risk on the vendor.  Both Operator & Vendor worked very closely together, with complete transparency.  It was well noted during the early stages of the project, that significant effort and investment in processes and tools were required from the start.  There was also significant investment in effort upfront for resolving the end-to-end architecture and detailed planning (based on Agile principles, it was a massive departure from the classic texts on Agile).

Both vendor and operator recognised the drive for better quality, the project's contract included the following goals for defects to be measured at each output stage of the project:

  • Zero Showstoppers per Component 
  • No more than 3 Major Defects per Component
  • No more than 10 Minor Defects per Component 

The above criteria was imposed on just the STB system alone. Recall the STB is a system that largely consists of a User Interface (EPG), a Middleware (The Operating System of the STB) & Platform Drivers.  The defect criteria was applicable to those STB sub-systems right down to individual component level.  Take for example, the Middleware-subsystem:  The Middleware system was componentized, broken down into more than seventy components - each component was owned by a component team. Each component had to be tracked subject to terms of discreet quality deliverable - metrics were mined on a continuous basis and trends reported as part of the Defect & Quality Management process.  The same diligence was equally applied to Headend & Backend components.

The Operator went further, imposing the following on each component, read below as Each Component:
  • Must have a Component Requirements Specification Document 
    • Each component requirement must map into a high level Product Use Case
  • Must be testable
    • Requirements-to-test-mapping matrix document
    • Automatic component unit tests must cover component requirements
    • 100% Test coverage of Requirements-to-tests
    • Must be testable in isolation - component unit test
    • Must be testable in a group - component group testing
    • Must be testable as a subsystem -  Middleware  tests
    • Must be testable as a system - full stack system tests
    • Test results be attached to release notes per release
    • Must have no Regressions - 100% Component Tests Must Pass
  • Must have an up-to-date API Interface Control Document
    • APIs must be testable and map to a component requirement
    • Higher level APIs must map to high level product use cases
  • Must have a Component Design Specification Document
  • Must have an Open Source Scan Summary Report
  • Must have Zero Compiler Warnings
  • Must have Zero MISRA Warnings
  • Must exercise API coverage 100%
  • Must test Source Code Branch Coverage, results at least 65%
  • Must test Source Code Line Coverage, results at least 65% 
With this degree of focus on quality which outlines in clear terms the expectations of the delivery, the vendors no doubt had to invest significant time, effort, and energy in installing quality management processes early on during the project.  The Operator has taken sufficient precautionary measures to ensure quality deliverables from its suppliers, so overall tracking quality became a natural part of the programme management process.

As we were on the receiving end of this quality expectation and had to ensure our deliveries met expectations, our project team was partitioned such that Quality & Defects were managed by extending the project team. We employed a quality evangelist, a seasoned technical expert that focused on the software quality deliverable. A project manager was used at key points in the project to focus specifically on managing the defect backlog.  A project administrator provided support to the project team in the areas of data mining and management, managing the internal defect processes (ensuring defect tracking tool was used correctly, information was correctly applied, etc.), and generating weekly defect metrics reports that was presented weekly to the customer (Operator).  The defect metrics was one way of measuring the completeness and maturity of the project, apart from being software development complete.  We had to report on every single deviation from the agreed criteria, trying to satisfy the customer's (Operator's) every demand.

To give you an idea of the amount of tracking, administration and management involved in just ensuring we met the quality criteria, you can view a sample template of the tracking spreadsheet here - see picture below:
Sample Tracking Tool (A lot of Project Management Effort)
It's been genericized for privacy reasons, but it gives you an overview of the complexity of just this one Middleware sub-system alone.  We had do this for key milestones, typical milestones for a STB project are: Zapper complete, Basic PVR, Advanced PVR, Progressive Download, Interactive Applications (Not sequential activities).  Just so you appreciate the context: This Middleware consisted of 80-100 components during the life-cycle of the project, spread across 3 continents, 4 countries, with a development team of 200 people. At the project's peak, there were around 350 people directly involved in the STB development activity, supported by a project team of 20-30 people also geographically dispersed.  My part as development owner was overall management of the development backlog. planning, issues and delivery, working through regional project interfaces...

In the remaining sections of this post, I'll attempt to describe what I've come to learn & consider as good practices for Quality/Defect Management to ensuring a successful outcome for most DTV STB projects (based solely on past project experiences).

In a typical STB project, there are usually more than one vendor involved. As vendors, it is in their best interests to support multiple customer projects at the same time, generally building upon a common software platform. These vendors can be viewed as traditional software vendors. The following players are involved: Chipset Manufacturer, STB Manufacturer, Middleware Vendor, Virtual Machine Provider, Application Vendor and Systems Integrator (SI).  The SI of course doesn't own any software components, but is primarily responsible for pulling the components together to provide a coherent STB build.  Each of the vendors will have its own internal processes to manage quality. They will also have their own internal defect tracking tool, with its own terminology that is well understood.  Some of these vendors operate quite independently, but when the STB stack is pulled together, it often involves collaboration between multiple parties (as facilitated by SI) in resolving issues.

Because there is no internationally accepted standard for defining defects, and taking the disparity between vendors into account, it becomes necessary for the DTV project team to ensure there is consistency in terminology across all parties. For example: A Showstopper means what it is, and nothing else; a Priority P0 is assigned by one authority only and no one else, etc.

Imposing common terminology upfront sets the stage for the programme, ensures consistency, avoids unnecessary noise (which wastes time) and promotes a common understanding and set of values across the board.  With a clearly defined criteria, teams can use the template as a handy look-up, it also empowers people to challenge certain defects, and is an enabler for everyone on the project to raise and classify defects with reasonable consistency.

The most important feature however is consistent representation. All vendors must understand the project's objectives and make the necessary adjustments to their internal defect tools.  When reporting defect metrics for the entire project, there is thus some confidence in the integrity of the data.

There is often confusion around Defect Severity versus Priority.  Priority calls are often subjective and usually at the discretion of the Product Owner or Delivery Manager accountable for delivery.  Severity on the other hand, can be more accurately defined, and can take advantage of a useful look-up table.  This helps developers, tests, integrators and managers alike, in setting severity consistently.

In most of the past projects I've worked on, there are usually the following defect Severity definitions: Showstopper, Major, Minor. In terms of Priority, some projects use separate Priority defines: P0, P1, P2; whilst others imply priority by the overloading the Defect severity, i.e. a Showstopper by definition is assumed priority P0.  As the project matures, the Product Owner/Delivery Manager gets more involved in defining the priorities, which may contradict the look-up definitions.  At launch stage, this is solely at the discretion of the senior stakeholder accountable for Launch.

Nevertheless, I strongly support the argument for consistency and common language. I have over time collected some useful tools for managing DTV projects, one tool is a useful Severity & Priority Matrix template:

Defect Severity Template
Defect Priorities Template
Download the Excel Template
Download the PDF Template

Recall a previous post that discussed auditing your project's processes. In a recent audit carried out on a project I wasn't primarily involved in, the recommendations around defect management, from the auditor S3, echoed much of the above templates that I'd already instigated in my project, prior to the audit exercise.

There was an additional recommendation of the option of Service Level Agreements in terms of response times for defect resolution that must be agreed with your various suppliers:

  • P0: Acknowledgement within 1 hour, Initial Response within 24 hours, Fix/Workaround within 48 hours
  • P1:  Acknowledgement within 1 hour, Initial Response within 2 Working Days, Fix/Workaround in next release or within 1 month whichever is earlier
  • P2:  Acknowledgement within 1 hour, Initial Response within 5 Working Days, Fix/Workaround before final release according to agreed schedule

You can also reduce the work on defect administration by architects (as the programme depends on architects assessing the severity of defects) by providing guidelines for priorities, for example the following are generally used for STB projects:

  • STB SI Stability Showstoppers
  • STB SI Smoke/Soak Test Regressions
  • Customer Sanity Regressions
  • Customer Acceptance Tests Showstoppers
  • Existing Showstoppers (oldest first)
  • Component Stability Showstooppers
  • Showstopper Feature defects
  • Major Defects
  • Features broken by Major defects

I've used variations of the above in past projects, I am currently using this in my present project. It works - but it requires some administration and consistent diligence!

Earlier I recounted some of the quality criteria that was imposed in a past project. Some might say that was quite a heavy-handed project; given the context and expectation, I would say the expectation was not that unreasonable, if not I think it was missing a few quality targets (such as Code Complexity, Cyclomatic Complexity, Function Points, Defects per Lines of Code, Defects per Functions, Defects per Region).

Not all projects need to define quality criteria down to that level of detail, it essentially depends on the nature of the project. Other factors include the maturity of your component suppliers. If your suppliers have earned a reputation for quality and have audit results to prove, perhaps they're a CMM level 3/4/5 company, or ISO9001 certified then that would naturally instill some confidence in assuming quality deliverables. Another factor related to component vendors is maturity in the marketplace - if your project includes mature, proven components that have a well-known track-record, the it's relatively unlikely that things will go pear-shaped.  However, if you're dealing with the somewhat unknown, unclear, where the level of uncertainty and risks are quite high, then you cannot ignore quality criteria.  You should have some way of defining your quality objectives for the programme.  At the very least, you should set the expectations of quality building upon best practices, and should go to the extent of auditing your supplier's processes to  increase the chances of your project's success.

Settling on a common terminology for defects as described above is the first step towards specifying clear, measurable, specific and timely quality criteria.  You could go down the Software Quality metrics route as discussed above if you are serious about your software.

Realistically however, if you're an Operator, your end result is defining the success criteria for the project delivery. Generally, no matter what development methodologies your component vendors adopt, or the integration strategy you define in terms of continuous integration & continuous delivery -- it is natural to approach STB projects using clearly defined stages, or in project management terms: Stage Gates.  At a high level, the stages represent feature completeness of the product:
Zapper > Basic PVR > Advanced PVR > Push VOD > IP VOD > PDL > Interactive Games > Launch.

In order to reach the Launch milestone, there are a few testing/stabilisation gates that need to be passed.  This is where the Common Defect Severity & Priority definitions and Delivery Milestones go hand-in-hand (most of the below concepts were used in the project I mentioned previously):

  • Milestone: Start Closed User Group (CUG) Field Trials
    • Criteria:  All Components Must be Functionally Complete:
      • Verified acceptable by component tests, system testing, and pre-field trial testing
      • Zero Showstopper defects from frequent use (e.g. normal end user, installer or customer-care user day-to-day usage) of product functionality in Functionality, Performance or Stability.
      • Product to be stable in normal end user, installer, customer-care user usage, such that it can continuously run without rebooting for >72 hours at a time.
      • Less than 5 Major defects per functional area in Functionality, Performance and Stability
      • Any Showstopper graphical bugs by exception.
  • Milestone: Start Wider Field Trials
    • Criteria: CUG Ends,  Release Candidate build is available
      • All product functionality available with Zero Showstopper defects in any area.
      • Product to be stable in normal usage, such that in can continuously run without rebooting for > 1 week at a time.
      • Less than 20 Major defects across Functional, Stability & Performance in all Functional areas - across the entire product.
      • All such defects to have clearly identified and agreed action plans associated with them and a forecast resolution of < 3 weeks.
      • Zero Showstopper defects.
      • Major graphical defects by exception.
  • Milestone: Launch - Go Live!
    • Criteria: Field Trial Exits, Launch Build available
      • Zero Showstoppers or Zero Critical issues whatsoever - any defect affecting revenue classified deemed as critical.
      • A level of minor defects that have no negative impact on customer satisfaction, which does not represent a regression of what is in the field already.
      •  Stability issues must be sufficiently rare as not to be expected to be encountered under conditions found in normal end user, installer or customer-care user usage.
      • Product should not crash or need to be rebooted.
      • Graphical and Performance issues should be of a nature such that they are not noticeable to most users using the box in normal end user conditions, installer or customer-care usage patterns.
      • Both above to be established through field trial surveys, with 95% of respondents confirming the software to be equal to or better than current infield software in terms of stability and performance.
In addition to the above set of criteria, it is also quite useful to breakdown the STB product into the key functional areas to track the impact of defects. By breaking down the product into functional areas, and tracking the spread of defects across these areas, the programme can gauge the overall health of the product.  The product owner is best placed to prioritise the areas to breakdown, but STB products are quite constrained and already have a well known feature set.  For instance, the following breakdown can be used:
  1. User Experience / Usability
  2. Finding Content via Service Information
  3. Finding Content via On-Demand
  4. Live TV Viewing
  5. Booking Recordings and Reminders
  6. Broadcast Recording - Schedule and Current
  7. PushVOD
  8. On-Demand Downloading
  9. Purchasing Content
  10. Parental Control & PIN Management
  11. Using the Planner / Playlist Management
  12. Live TV Trick Modes
  13. Playback Trick Modes
  14. Managing Resources (Tuner Conflicts)
  15. Interactive Applications
  16. Usage Monitoring
  17. System Operations
  18. Diagnostics / Health Check
  19. CA Callback
  20. Internet Connectivity / Browsing
For each of the above functional areas, you can define more targeted quality criteria.  This helps the project team direct focus and attention intelligently, working towards clear, specific, measurable and timely objectives.  The functional areas gain increasing focus as you approach launch, and it is generally within this phase of the project that we then start making launch-critical decision, concessions and waivers.  So understanding the critical criteria for business decisions is helpful.


DTV projects are becoming increasingly more complicated. Traditional Operators are taking risks and doing more enhancements than perhaps five years ago, where the broadcast system was fairly stable, and all major enhancements were more STB-centric than headend.  With features like PushVOD, IP-VOD, Progressive Download, Recommendations, Audience Measurement for Dynamic Advertising and Recommendations -- these are big-impact features that touch the entire value-chain: STB, Headend, Backend, Infrastructure components are all impacted.  Overall your programme needs to track progress for the entire value chain, and quality needs to be managed effectively.

This largely becomes the responsibility of the Systems Integrator (SI) assigned to your programme, from an Operator's perspective.  For an individual product vendor's perspective, you need to align your existing internal processes to match the requirements and expectations of the programme you're delivering to.

Having a clear Defect Management Policy that not only defines what Defect Severities & Priorities as described above, but also describes the processes for raising defects, assigning to component owners, required information, etc.  This document must be published and distributed to all vendors in the programme.

It is quite obvious from an SI perspective why you need to define a clear Defect Process and Workflows, but if you're a vendor delivery Middleware or UI, with your own established tools and processes, you might question the need for creating a separate process for a project in the first place.  Generally the reasons behind this are the following:

  • In some customer projects, general product processes will not apply. There will be mismatch between internal definitions versus customer expectations
  • Defects will be raised internally by your own development/test teams, as well as by the customer and system integrator. Your team need to understand where different defects come from, and priorities
  • Customers generally will use a different defect tracking system to manage all their supplier deliverables.  For example, S3's Engage Portal is increasingly being used as the central hub for release and defect management, whilst vendors may choose to use Rational Clearquest, BugZilla, Spira, Jira or TFS.  Your team needs to understand the mechanics around this: how does the customer and vendor ensure the trackers are synchronised?? This generally requires a custom process or tool.
  • In terms of integration, release and branch management - as a vendor you will be supporting different branches of your product.  Your product team need to understand what the policy is for fixing defects on your main product trunk versus customer branches - a customer might be given higher priority than your product development, this process needs to be made clear to your development/test team. Do all your component teams understand how to manage defect fixes across multiple branches??
  • Quality of the release is measured according to the number of defects open - defect metrics are important to the customer. Your processes will have to change to support the metrics needs of the customer, your teams need to learn about maintaining accuracy of data, hence a clear defect process is required.
If you have never created a Defect Process/Policy document before, here are a handful of questions to guide you along:
  • Why do you need a separate Project Defect Process anyway?
  • Can you take me through a simple for work flow of a defect in in my project?
  • Who can raise defects in my project?
  • What is the project's definitions for severity?
  • How does the project define defect priorities?
  • Are there any tools being used outside of our internal defect tracking tool?
  • What should you do if your defect is lacking in detail and you need to find more info?
  • Who is allowed to postpone a defect?
  • Who is allowed to reject a defect?
  • Who is allowed to close a defect?
  • Who is allowed to duplicate a defect?
  • Who is allowed to clone a defect?
  • Who is allowed to move a defect to another component?
  • Who is allowed to open enhancement requests?
  • Who should test and verify a defect is fixed - i.e. where is the ownership?
  • How do we handle defects from an external tracking system not our own?
  • How do we handle multiple projects for the same customer?
  • What do you do when you find a defect that is common to multiple customers?
  • What do you do when you find a defect on one customer branch that is relevant for another customer branch?
  • What is the priority for fixing defects on customer branches?
  • What do you do if you moved forward in your sprint but the customer requires an urgent fix?
  • How to use your defect tracking tool - mandatory fields, information required, requirements for log files, etc.?

If everyone in your project can answer all of the above without needing it documented, then great - but I can guarantee you that there's bound to be confusion and ambiguity in this area - that's why the programme management team should dedicate time and energy to bed these processes down.  It will help your operation in the long run!

Ensure consistency of data
Earlier I mentioned the disparity of bug tracking systems that maybe in use by different vendors (if you're the customer) or by your customer (if you're a vendor delivering to a customer). Additionally the System Integrator assigned might opt to use a completely different system as well.

Just take a look at what the market has to offer: comparison of different defect tracking tools. There is no perfect tool that will meet all your needs, typically these tools provide enough of a foundation for best practices, it becomes complicated as the reporting needs for the project matures, eventually resorting to custom scripts and tools that sit on-top the defect tool to provide the information in the format and view you need.  I've got a deep background for IBM Rational Clearquest as I've used that tool for almost my whole career to date, which makes me pretty biased to the Rational Development/Quality philosophy.  Yes, that tool can be pretty heavy handed, requires a lot of administration, and depending on the size of your organisation and maturity of products, the centralised versus distributed deployment models can be somewhat of a pain.  Nevertheless, with an accessible API, one can create reports and dashboards relatively easily; automation tools integrate well too.  Coupled with Rational ClearCase, you then have quite a solid tool for your software management policy. I have used other lightweight tools like BugZilla, Redmine & Roundup -- but I found those to be pretty much featherweight contenders not fit for the heavyweight requirements for a serious DTV Programme.

In my current project we have a System Integrator using Spira, one Application development team using Spira as well, another team using Pivotal, a team using Jira, one vendor using TFS, and another vendor using IMS.

So the challenge then is how do we maintain consistency of data? We cannot force our vendors to change tools, but what we have to ensure is that the mappings of defects reflect the common terminology as noted previously. That's the first point: ensure all tools comply with the project's definitions for different types of defects.

The next challenge is ensuring data synchronicity. As a vendor, how do you ensure that defects raised by SI find their way back to your internal defect tracking system? As a customer or SI, how do you ensure that your vendors are not hiding crucial defects in their internal tracking systems that should be exposed to the customer?

Maintaining consistent data is key to enabling more accurate production of defect metrics. It also allows the project to have a unified view of the end-to-end system, confident that all parties are using the same terminology that is reflective in the data being reported.  A critical phase of reaching the Launch stage of a DTV project is a period of focused defect resolution and fixing.  Based on the rate of defects being submitted and fixed, we can use this information to better predict the closure of the project.  Ensuring consistency of data also prevents us from not seeing the true picture - the classic tip of the iceberg scenario: the customer/SI might have just a shallow view of the true defects status, there maybe hidden defects your vendors are not publishing that could influence the outcome of the project.

S3 have developed a portal, called Engage, intended to better manage the system integration and global management of an operator's delivery. It is more than just an issue tracking system, offering a repository for documents (not a document management system) as well as a release repository (instead of having separate FTP sites floating around).

In the example past project I mentioned earlier, Engage was the primary tool being used by the customer to manage all their suppliers. We started off by providing just the Middleware sub-system but later also provided the EPG, and then also took over system integration. During the early days of my managing the  Middleware, we realised there was a disaster brewing because of the mismatch between Engage and Clearquest, the customer kept asking about issues we weren't really focusing on. We did have one person assigned to tracking Engage but it was not a full time activity, the process was manual and quite tedious and error-prone (manual copy-and-paste) from one system to another. This clearly wasn't efficient. We introduced automatic importing from Engage-to-Clearquest, and also exported from Clearquest-back-to-Engage, ensuring that both Clearquest-and-Engage were in sync. Being on the same page with the customer makes a whole lot of difference!

Take a look at a typical workflow required to maintain synchronicity - this is based on how we solved the Engage-Clearquest problem (genericized for privacy reasons) for our Middleware component (PDF, Visio):
Syncing Engage-Clearquest Workflow

Because the Middleware is a fundamental component to a STB-stack, offering services to many consumers, defects will arrive from various sources. The Engage portal was used to track the other component vendors, typically the EPG developers, SI & Test teams.  Every day the customer would raise issues on the Engage Middleware tracker, as well as the other trackers (SI, xEPG, ATP). Issues arrive on the Engage tracker after an internal review process by the customer. We enforced a daily defect scrub/review process, involving our lead architect, component technical leads, customer test analyst lead, customer system integration lead, and technical project managers. Everyday at 10AM, the newly submitted defects would undergo a review "Scrubs".  For each issue that was assigned to our  Middleware tracker, the customer had to ensure sufficient detail was captured in the description to allow us to start our investigations.  We created a custom tool that ran every night like clockwork, at 19:00PM, imports all new Engage issues automatically raising new Clearquest defects (CQs). The tool enforced strict rules according to the status of the Engage item, one rule was that only those Engage items assigned to us (a.k.a. Vendor Owner) will generate a new vendor CQ, assigned to a generic owner called ENGAGE_MW for  Middleware issues.  There were cases where old Engage items were re-opened, and a new CQ would've been auto-generated, even though the previously assigned CQ was still in the Open State & assigned.  Every morning, the scrub would agree to accept an issue as requiring further investigation in the  Middleware , and will move the CQ from ENGAGE_MW to the respective  Middleware component as assigned by the scrub for initial investigation, we'd add comments like "This defect was reviewed in the daily scrub call and we think component XYZ is best placed to start the investigation" or "There is insufficient information to assign to a component, this needs to be triaged further by STB SI".

To maintain consistency of data, we had to ensure that the states for Clearquest defects were mapped to the states in Engage.  The customer generated reports from Engage, which cross-referenced our internal CQs from Clearquest.  We maintained Clearquest reports which was also communicated back to the customer in the form of weekly Defect Metrics reporting.  Hence the need for specifically defining a workflow that established mappings between the different defect tracking tools for maintaining consistency of data.

I am quite certain this problem will creep up on almost every major STB project, so hopefully I've given you an idea of the work involved.  We had a project administrator involved full time to the activity of ensuring the defect tracking systems were synchronised, that information was accurate and that information integrity was maintained.  This same administrator also ensure that the Showstopper/Major/Minor was equally mapped to the Critical/Major/Low translations of the different tools.  More importantly, when there were discrepancies in the metrics reporting, we would go to this project administrator as the first port of call for clarification.

Defect Metrics is not just yet-another-administrative-task-by-project-management-to-keep-themselves-busy-and-create-annoyance for development teams.  Defect metrics is not about just reporting defect counts using visually appealing graphs and figures again, to keep senior management happy.  Defect metrics is also not an an over-the-top management intervention that goes against Agile Development philosophy.

Defect metrics provides valuable information relating to the health of the overall project. It can provide useful insight into problematic areas, highlighting areas of bottlenecks, identify areas for improvement -- all useful pieces of information for the project management team to make informed decisions, taking corrective action.

Applied correctly, defect metrics can be an invaluable tool providing input into the discussions around a project's success criteria and probability for launch.  Recall the earlier delivery milestone criteria for a STB project launch: Functionally Complete, Start of Closed-User-Group Trials, Start of Field Trials to Final Launch. To reach each one of these milestones, your project needs to progressively improve the quality of the defects and stability of the system.  Without useful metrics to hand that can be used to highlight the current trend of defects in your system, versus a projected view (extrapolating trends from previous performance) of likelihood of actual project completion -- you have no scientific or factual basis to justify confidence in reaching your milestone deliverables, apart from your hunch-base.

This is just not my opinion - there is a vast body of knowledge around the subject of Software Quality Measurement (some supporting evidence will be presented now, followed by a real-world example):

A DTV project is a naturally software-intensive system, and as such, a key measurement of software systems is the latent state of bugs or defects. Taking a few words out of Steve McConnell's Software Project Survival Guide: How to be Sure Your First Important Project isn't Your Last (Pro -- Best Practices) (Chapter 16 on Software Release):

At the most basic level, defect counts give you a quantitative handle on how much work the project team has to do before it can release the software. By comparing the number of defects resolved each week, you can determine how close the project is to completion. If the number of new defects in a particular week exceeds the number of defects resolved that week, the project still has miles to go... 


Generic Open VS Closed Defect Trend (Shows ideal - fixed overtakes open, project in good shape)


If the project’s quality level is under control and the project is making progress toward completion, the number of open defects should generally trend downward after the middle of the project, and then remain low. The point at which the “fixed” defects line crosses the “open” defects line is psychologically significant because it indicates that defects are being corrected faster than they are being found. If the project’s quality level is out of control and the project is thrashing (not making any real progress toward completion), you might see a steadily increasing number of open defects. This suggests that steps need to be taken to improve the quality of the existing designs and code before adding more new functionality…


According to the Software Engineering Book of Knowledge (SWEBOK Chapter 11 on Quality), this is what they have to say about metrics and measurement:

The models of software product quality often include measures to determine the degree of each quality characteristic attained by the product.  If they are selected properly, measures can support software quality (among other aspects of the software life cycle processes) in multiple ways. They can help in the management decision-making process. They can find problematic areas and bottlenecks in the software process; and they can help the software engineers assess the quality of their work for SQA purposes and for longer-term process quality improvement... Finally, the SQM reports themselves provide valuable information not only on these processes, but also on how all the software life cycle processes can be improved...While the measures for quality characteristics and product features may be useful in themselves (for example, the number of defective requirements or the proportion of defective requirements), mathematical and graphical techniques can be applied to aid in the interpretation of the measures. These fit into the following categories: 
Statistically based (for example, Pareto analysis, runcharts, scatter plots, normal distribution); Statistical tests (for example, the binomial test, chi-squared test); Trend analysis & Prediction (for example, reliability models).
The statistically based techniques and tests often provide a snapshot of the more troublesome areas of the software product under examination. The resulting charts and graphs are visualization aids which the decision-makers can use to focus resources where they appear most needed. Results from trend analysis may indicate that a schedule has not been respected, such as in testing, or that certain classes of faults will become more intense unless some corrective action is taken in development. The predictive techniques assist in planning test time and in predicting failure....They also aid in understanding the trends and how well detection techniques are working, and how well the development and maintenance processes are progressing. Measurement of test coverage helps to estimate how much test effort remains to be done, and to predict possible remaining defects. From these measurement methods, defect profiles can be developed for a specific application domain. Then, for the next software system within that organisation, the profiles can be used to guide the SQM processes, that is, to expend the effort where the problems are most likely to occur. Similarly, benchmarks, or defect counts typical of that domain, may serve as one aid in determining when the product is ready for delivery.


And last, but not least, there is actually a website dedicated to the Defect Management process: www.defectmanagement.com  which basically says much of the same as above in more palatable English:
Information collected during the defect management process has a number of purposes:
To report on the status of individual defects.
To provide tactical information and metrics to help project management make more informed decisions -- e.g., redesign of error prone modules, the need for more testing, etc.
To provide strategic information and metrics to senior management -- defect trends, problem systems, etc.
To provide insight into areas where the process could be improved to either prevent defects or minimize their impact.
To provide insight into the likelihood that target dates and cost estimates will be achieved.


Management reporting is a necessary and critically important aspect of the defect management process, but it is also important to avoid overkill and ensure that the reports that are produced have a purpose and advance the defect management process.

Real-world examples of Metrics Reporting
Drawing again from the example project, as highlighted in the beginning, there were clear milestone deliveries communicated at the project's initiation.  We had to start measuring our defects status early on in the project, despite having not reached functionally complete status.  Some people are of the opinion that defect metrics should only start once development phase is fairly mature and we're into our integration & test / stability phase, as doing this any earlier would cause undue noise to the development teams, and unnecessary management administration.  Whilst others take the view that defects should be monitored early, from the development phase, right through the end.  I share the latter view, as I believe that early monitoring of defects during the development phase is bound to highlight problematic areas in requirements, design, architecture and coding, that if left unresolved until much later in the project would be a costly exercise.  I also believe that continuous integration and testing early, surfaces defects earlier than later.

Going back to the example project, we had to supply our customer with weekly defect metrics reports.  We also had to extrapolate past trends in predicting the future outlook.  We were also then measured and tracked on our predictions and were taken to task if we were woefully out with our predictions!  I was not the one producing the reports to the customer, that was handled by the delivery team -- however my middleware component was the major supplier to the programme, so I took it upon myself to maintain my own internal view of the metrics.  This was a contentious issue at first because there were discrepancies with what was being reported to the customer, versus my own internal calculations.  This actually struck a chord with the senior account holder, who based his method of metrics from sound judgement and experience, whereas I wanted to be more academic -- suffice to say, I did eventually come around to the senior manager's way of thinking, I've come to respect his hunch-base, wisdom earned from a great track
record of delivering successful projects in the past (he's an inspiration to many!).  I have also come to appreciate that if you've delivered projects before, that is valuable experience, that based on your instinct alone, without requiring a detailed plan, you can fairly accurately predict when or how long a project would take.  I had a recent experience where I had to stand my ground based on my own experiences and learning to base my own project's outcome of success solely on my past experience, or hunch-base.  The term hunch-base is from Tom Demarco's novel The Deadline : A Novel About Project Management which every Software Manager should read by the way...

Manager's crude way
We relied on a very basic approach (not overkill) to defect prediction. The metrics were based solely on defect counts alone, using a history dating back to the previous four weeks.  The number of Open/Closed defects was based on a rolling four-week period, based on the number of defects closed in this four-week period, predicted the future that showed the number of days remaining to fix all open defects.  Using the milestone criteria, the defect metrics report tried to establish predictions around those dates.


My own internal metrics predictions
- Download My Excel Tool
There are more deeper analysis and statistical techniques to mine data and make defect predictions, even down to using a mathematical model.  I did not go down that route, even though I was really tempted to do so.  Instead, I went a step further than the crude approach and based my predictions on the trends of submitted versus closed rate for all defects, with a focus on Showstoppers & Majors. Taking into account not only the defects closed in the last week, but also those submitted, if you mine enough data you can then rely on a statistical average for open/closure rates to predict when the project or component is bound to start the downward trend to reaching zero.

I went to the extent of creating a model in Excel that basically played with two variables: Submit Rate vs Closure Rate.  To get to launch, and to get to the ideal that your closure rate must surpass the submit rate, the following could happen: Assume your submit rate decreases over time and/or your closure rate increases over time.  The chances of your submission rate decreasing over time is much higher than your closure rate increasing over time.  Why??  Because over time we have to assume that the quality of the system is increasing over time and that testing will find less and less defects.  It is unrealistic to assume your closure rate is going to continuously increase over time because once you've established your teams capability for closing defects, i.e. their maximum throughput, closing a Showstopper/Major defect will take as long as it takes.  It is unlikely your team size is going to continuously change or that your team will be exceeding expectations. Generally as we reach the launch phase, the teams will have been working at full throttle, getting any more performance gain out of them is going to be a tall order.  Hence it is best the closure rate is assumed constant, and hope for a decline in submission rate over time.  The model was still crude in that it assumed a uniform reduction in submission rates -- nevertheless it was still a model that could be used to output a prediction based on some assumptions.  Looking back however, the model did come pretty close to reflecting the eventual end-date.  The snippet below shows the front page of the tool: It can be used to track separate components or the Middleware as a whole.  In the figure below, it shows the status & prediction for reaching the launch milestone for the entire Middleware component. It also showed the current trend at the time that the Middleware component was looking in good shape as we started to see at last that we're closing more defects than were being submitted:

Defect Prediction Tool (Download the Excel Template)

Some example metrics I like to report in my projects


Defects Dashboard Summary:
  • Total Open
    • Submitted
    • Under Investigation
    • Implemented
    • Ready for Test
    • Verified
  • Total Closed
    • Rejected
    • Duplicated
 Age of open defects:
  • By age, calculate the duration the defect has been open (from submit date to present date), along with the owner, and the state of the defect (submitted, assigned, etc.)
  • Also include views on severity & priorities  
Trends:
  • Week by Week view (ability to generate a table if needed) preferably a graphical view of the following:
    • Total Open trend (delta between current week & previous)
    • Total Closed (deltas)
    • Submission rate VERSUS Closure Rate
      • This graph is helpful as it’ll show you if the project is trashing or not. When you ready for launch, the trend should clearly show Closure rate consistently higher than submit rate
      • The data must be readily available, because it’ll help you predict the defect rate leading up to launch. We should be able to predict, based on past history of defects submit/close rate, the likelihood of reaching a stable build
 View of defects by Feature:
  • A Pie-chart giving us the breakdown of defects by feature / user story. This will show us how complete we are functionally
  • This depends on whether there are appropriate fields being used in your defect tool to track these
  • Feature priority must also be taken into account – probably a separate pie chart. This will show you which areas to concentrate on
View of defects by submitter:  Need a way of checking where the defects coming from:
  • UI developers
  • UI Testers
  • SI Integrators
  • SI-QA Testers
  • Customer ATP
  • Field Trials
Time it takes to close defects:
  • You need to answer: How long does it take to close a Showstopper/Major P0/P1/P2 on average?
For the SI projects:
  • View defects by Component: Drivers, Middleware, UI
  • For each component, apply the same metrics as above (Age/Trend of Submit versus Close, etc)
Measuring development schedule also contributes to overall metrics and is related to overall Defect Metrics reporting
There is usually a development phase for one major component of the STB project, could be a Middleware component or the EPG Application / UI.  The completion of the development phase will obviously impact the project's launch criteria, it is therefore a natural requirement to track development as part of the overall metrics reporting.  What these metrics will focus on is not only the defects resulting from development, but the productivity of the team itself.

In the example project, we had to track and report on our Middleware current status against planned schedule, and include predictions of time to completion, including a prediction of the likely defects to encounter at the end of the development phase; followed by a trajectory or glide-path for time to completion of defects.

The following topics can be considered useful reflection points for metrics regardless of the software component or development methodology (assumes Agile):

  • What is the feature breakdown?
    • How many features development complete? 
      • How many user stories implemented with no outstanding bugs?
      • How many user stories implemented with outstanding bugs?
      • How many user stories to be planned?
      • How many user stories blocked?
      • What is the prediction for completing a feature?
    • Predictions for completing remaining features?
  • Measuring Sprint Progress in more detail:
    • Planned versus Actuals being reported for each user story
      • How many stories completed on time – development, tested with no bugs??
      • How many stories missed the planned completion date but still delivered within the sprint?
      • How many stories missed the sprint completely, despite not being blocked by any dependencies?
      • How many stories were blocked by unforeseen issues?
        • What issues were these?
        • How can we take corrective action to prevent blocks from happening again?
  • Measuring Risk-Mitigation stories:
    • How many risk mitigation stories are on the backlog?
    • When is it predicted to close down these risk mitigation stories?
    • What are the consequent stories dependent on the outcome of risk mitigation stories?
  • Adding Other stories to Sprint Backlog:
    • STB SI will be influencing the objectives of the sprint – SI will provide a list of defects that must be fixed for the next release. This needs to show up as a story
    • Defect fixes must also be allocated a story – accounts for time
  • Overall burndown of Component completion estimations
    • Given the following things can happen during a sprint:
      • Developing new features
      • Risk mitigating features for future sprints
      • Fixing of defects raised by dev testers / developers
      • Resolving SI objectives
      • Supporting release process
      • Pre-planning
    • Can we quantify more clearly, even though it's an estimate – of the likely burndown trend to result if everything is accommodated for – where does the end date come out??
Other Useful Example Metrics
The picture below illustrates a snapshot in time of how we used metrics reporting over the life-cycle of the example project. This should give you some idea of what it involves:
Tracking Metrics through different phases of a project (12 months to Launch)
The first row in the above dashboard tracked the  Middleware test coverage in terms of total test cases defined. written, run, passing & failing. The point of those curves is to illustrate the gaps between the various areas:

  • a gap between defined and written test cases highlights the backlog of work remaining to implement the test cases as planned [ideal is to have defined to equal written]
  • a gap between written and run indicates the bottleneck with executing test cases (test system was fully automated and required to complete within 48 hours) [ideal: run equal written - all implemented tests must be run]; 
  • a gap between run and passing highlights the quality of the test cases or quality of the  Middleware [ideal: all tests run must pass];
  • a gap between failing and passing indicates how far the component is away from meeting the quality criteria [ideal: zero failures]
Over time as the project reached its end we had close to 2000  Middleware tests alone, with a pass rate of 95%. We extended the tests to system level testing - basically those  Middleware tests that failed but didn't manifest themselves at system level was given low priority.

The second & third rows focused on All Open Defects, Showstopper & Major defect trends, with the aim of highlighting the gaps between reality and planned targets.  We also had to predict a "glide-path" to reaching the target, which is what the curves in the second column highlights. These curves were getting incredible complicated to produce based on manual administration, we dropped those prediction curves and focused our efforts on burning down as many Showstoppers/Majors as we could.  

In reality, your defect metrics reporting will undergo several iterations before the project settles on what is realistic, simple, understandable, easy to maintain and track. Hence why the senior stakeholder went down the practical route and established predictions based on the performance of the last iteration and predicted the burn-down based on the remaining days to reach the target.

Below is another example of how to communicate the progress of your software components in reaching the agreed targets:
Metrics reporting/predicting time to complete defects to meet Launch Criteria
In the above picture, we focused on the top components that required attention, currently failing the launch criteria.  Management used this information and implemented recovery actions where possible (e.g. beef up the team by using developers from other component teams, focused one roof integration (ORIT) sessions); but in some components like the Streaming Manager, we just had to accept the status as is because it was one of the most complicated components in the Middleware, responsible for all features of media streaming - core group of technical experts very difficult to clone (as evident by the small number of open defects but predicted the longest time to complete).

We also tracked the classic defect counts of Submitted VS Closed:

Classic Defect Submit/Open/Closed Trends


The main focus of these curves, as mentioned above in citing Steve McConnell, is to measure how the project is managing the defect closure rates: essentially, are we in control of our defects? The curve should highlight this quite nicely, the goal being to be as close to the total submit/open line as possible, at best, to be able to close more defects than submitted:

  • The implemented curve is the current total of all defects which have been implemented or closed.
  • The gap between Implemented and Submitted reflects the amount of development work yet to be done.
  • The gap between Implemented and Closed reflects the amount of work to be done by Integration / Test teams for verification.
The trend did highlighted the classic creep in defects during the early stages of the project, although we were continuously developing and integrating / testing at the same time.  Eventually though, the trend did match the classic outcome of peak in submissions followed by a decline, then overtaken by the increase in closure rate. 

Measuring Rejected and Duplicates
A significant amount of time can be wasted in the areas of development and system integration, investigating issues that turn-out to be non-issues; or investigating defect reports with poor quality information; or also time is wasted investigated problem reports that have been previously been reported on (duplicates).  To the project manager this lost time cannot be gained, it's time wasted, and for all intents and purposes you have aim for maximum efficiency, eliminating the waste.  Having access to metrics reporting the incidence of Rejected/Duplicate reports is definitely useful in highlighting problem areas, without having to revert to detailed root cause analysis.

Take a look at the picture below: It is immediately apparent that a high proportion of defects being raised by the customer test teams are rejected or duplicated. At some point in the project, this amounted to more than half the total of customer raised defects.  This alerted us to instigate stricter controls over the quality of information being reported, which resulted in us enforcing the daily defect scrubbing process as discussed in the opening sections of this post.  Over time the quality of the defect reports did improve and the number of false defects reduced, saving us some valuable developer and integrator time.
Rejected/Duplicated Trends - Aim is to minimize false defects
Other Reference Examples

Report Metrics to the Executive Committee

Communicating metrics to the senior executive committee on your project is of crucial importance to ensure that the necessary decision-makers have the correct visibility and understanding of the true status on the ground.  Typically you would focus on the high level metrics across the Programme, focusing on specific vendors and trends overall for the Programme. Below are a few samples of interesting metrics that can be digested by the ExCo.  Whilst I've not read the complete book myself, I have interacted with many senior management people who highly recommend The Visual Display of Quantitative Information; and I've been around many executives who insist on visual information without the detail so much so that I myself have become quite the visualisation guy: pictures convey the message much clearer than having someone try to explain and show you numbers!

Here are some example metrics I've used in the past that have helped in conveying the message of the programme - The intent should be self-explanatory:
Defect Metrics Report for Exec Committee
Test Coverage Metrics for Exec (How far away are we from ATP/Launch?)


Implement Root Cause Analysis (RCA)
Again, there is a vast body of knowledge on RCA: Wikipedia, SWEBOK, CMMI. This site provides useful background information to tackle root cause analysis that I won't detail here. Measuring quality & defects go hand-in-hand: if the trends reflect an unusual increase in defects, or your test results produce fluctuating reports (e.g. constant but erratic regressions) and you detect general ambivalence from various teams, then those are your typical clues to instigate further investigation - to root out the causes of the fundamental problems.

RCA is all about learning from previous problems, seeking out ways to prevent similar problems from recurring in future, or at least will help you spot problems sooner than later.  By carrying out RCA the project teams (developers, testers, integrators) themselves have an opportunity to learn some very specific lessons relevant to the way they work, whilst the management team takes the big picture view in identifying areas to improve the processes in those areas.

In the area of RCA for defect management, there is a large reliance on availability of data. The data is your starting point for the first pass analysis.  Mining data from your defect tracking tool, you can look for clues: provided the defect tool is being used correctly.  Hence further emphasising the need for a clear Defect Management Policy that imposes rules on how the defect tool should be used, the mandatory fields of information, guidelines of what engineers/testers should communicate, etc.  Many technical people (developers/integrators/testers) often make the mistake of assuming defect tracking systems as an annoyance - administrative burden -  and seek ways to reduce the time spent, for example: automating the import of information. Whilst there's nothing wrong with automation, RCA seeks out worthwhile information: What went wrong, How did you fix it, What was the inherent cause for the defect, etc. Spending a little time explaining the situation in the defect record not only provides valuable information to the RCA administrator, but also would save time for people investigating similar defects in future.

Assuming you have a mature Defect Management System in place, the next step is to ensure your project or organisation is receptive to doing RCA, as it is a fairly intensive process, requiring access to your project's database, and access to engineers/testers - as much of the interaction is personal and through meetings (there is only so much one can infer from data metrics. To get to the bottom of the problem, a face-to-face, heart-to-heart is required).  You need to be ready to implement corrective actions that, if implemented correctly, will prevent certain defects from recurring.

I've not actively managed an RCA process myself, although I did instigate the activity in the past; and contributed information to facilitate the process. My part is more an observer however, as mentioned previously we had a specialist Quality expert that managed RCA for the example project - I'll share a few snippets of info here, since I'm sure all DTV projects will experience much the same.

The picture below is just one example of RCA metrics worth reporting:
RCA Trends: (Top) Quality of Defect Info - (Bottom) Root Causes Assignments
The above example illustrates the tracking of RCA over a period of time (11 SI releases, releases a 3 week cycle, so 33 weeks of data). Based on the analysis and feedback, we unearthed the following problems/resolutions:

  • Quality of Defect Information captured in problem reports needed much improvement
    • Instigated stricter defect reviews, the daily scrub process rejected poor quality information, assigning defects back to the submitter requesting missing information.
  • Component Design Flaws
    • Project management team enforced stricter controls over the "Definition-of-Done": Design reviews and sign-off required
  • Coding Mistakes / Errors
    • Project management team drove through code review training exercises
    • Code Review training became mandatory learning
    • Introduced further code quality checking into continuous integration system (measuring complexity)
    • Introduced Static Analysis Coding Tools to identify and trap hard-to-find defects; consequently the static analysis tool in itself was used to train engineers
    • Ensure test harnesses and tools are free of compiler and MISRA warnings themselves
    • Mandatory memory leak testing & tools introduced as part of release process
    • Better use of Code Review techniques
      • Peer programming
      • Face-to-Face review
      • Use online code review tool to facilitate collaboration
      • Open the code review to teams outside project (worked well to a point)
    • Too much pressure from project management
      • Defects take time to investigate and resolve, sometimes this is not appreciated by the management team.
      • PMs acted as deflectors to customer, buffering as much as possible leaving the engineers alone to focus on fixing critical issues
  • Architecture / Requirements
    • As part of architecture design, introduced section to detail specific error handling conditions
    • Improve system-wide knowledge across the project team
      • Reduce the component-silo approach to working
    • Reduce conflicting requirements by ensuring cross project architecture reviews
    • Aim to reduce ambiguity or "open to interpretation of implementer" in interface specifications
    • Prevent defects in requirements in the coding/testing phases because it's a costly affair - instill stricter requirements reviews, often involved multi-project architects to avoid conflicting requirements
  • Other / Unreproducible
    • Ensure test bit-streams match desired specification and don't defer to live stream
So if you're delivering software components to a STB/DTV delivery, and your components have a significant development phase, it is worth you planning in strategic points for RCA, as a way to improve your overall quality of your deliverable!

This piece of course will not be complete if I don't mention the classic, oft repeated and self-explanatory model of the cost-of-fixing-defects through different stages of the project:
Classic Defect Cost/Impact

Similar Cost Model from IBM


Conclusions

Defect Management is a key component of managing a DTV programme.  Measuring quality by means of defect metrics targeting clear milestone criteria is an effective way of tracking the progress of the project, the information can be used in various ways to communicate how far or close you're away from/to reaching the launch requirements.  There is a wealth of information around Software Quality Engineering; I've shared some experiences that have proven to be effective in real world projects.  Always keep a realistic hat on, avoid overkill and the pitfall of applying process-for-process-sake. Instead focus on the measurements that count, and depending on the growth or strategy of your organisation, think about applying some of the best practices in the background, without jeopardising your current project commitments, treating it as an investment to better improve your future projects....

I've presented a somewhat detailed approach to Quality Control for DTV Projects. I hope you can take away from this the following points, in no particular order:

  • Walk-the-Talk  (Implement the theory practically and see real results)
  • Have Accountability (Assign a custodian to the enforcing the quality deliverable)
  • Enforce Process at All Stages (Find the right balance of process and be diligent about it)
  • Ensure Feedback and Lessons Learnt (Metrics reporting and Root Cause Analysis)
  • Get buy-in throughout the value chain (Your Programme team must accept this approach to Quality)
  • Make sure you measure the right aspects (The value-add)
  • Don't forget the business objectives (NFRs), adjusting the process based on the level of quality required
  • If you get it wrong it's going to cost you time and money - and possibly your position in the market (Lean on people who've done this before)



Disclaimer: The views expressed in this post are based solely on my own professional experience and opinion (drawing upon both past and present projects). Whilst I've based the information on a real-world project, the data was normalised and kept generic-enough not to implicate/breach any company-sensitive policies (in the interest of professional knowledge-sharing).